Installing Mechanical/Electrical Systems in a Road Tunnel
Helping the project team visualize the contractor’s planned sequence for systems installation in the upper roadway of a large-bore tunnel. Each line segment was linked to one activity in the Primavera P6 schedule (161 total activities) for rapid updates each month. The 3D rendering was inserted on top of the chart to provide a helpful visual aid for discussions about the work.