Coordinating Staging Area Handovers between Contractors
This swimlane schedule answered the question “When are we required to hand over our staging areas?” and “What’s left to do in each area?” Summary activities were linked to the contractor’s P6 schedule for rapid monthly updates. This schedule was shared with contractors, construction managers, program managers, executives, and 3rd parties, all of whom needed a better way to see how this critical-path handover between projects was progressing.